- Switch and Breaker
Scheme # 3
To
prevent operation of switch A when breaker B is closed.
Circuit cannot be cleared until proper supervisory key
is obtained.

Breaker
B and switch A shown closed. Key A-1 held in breaker interlock.
Key A-2 retained by supervisor.
|
|
1.
2.
3.
4.
5.
6.
7. |
Obtain key A-2 from supervisor.
Open breaker.
Insert key A-2 in L-O interlock on breaker B and turn
key A-1 to lock open. key A-2 is now held and key
A-1
is free.
Insert key A-1 in L-O-C interlock on switch A and
turn
to unlock.
Open switch A.
Turn key A-1 in L-O-C interlock on switch A to lock
open. Key A-1 is now free.
Return key A-1 to breaker interlock and unlock for
operation during service period. |
Reverse
sequence to restore service. |