Interlock Application - Breakers and Generators

Scheme # 35

To prevent paralleling of any sources while allowing switching of the loads to alternate sources.

Interlock Application Scheme # 35 - Breakers and Generators


Breaker A is closed to supply load M. Breaker B is closed to supply load N. Tie-Breaker C and generator breaker G are locked open. Key A-1 is held in the L-O interlock on breaker A. Key B-1 is held in the L-O interlock on breaker B. Tie-Breaker C cannot be closed unless either breaker A or B is locked open. Generator breaker G cannot be closed unless breaker B is locked open. Tie-Breaker C interlock has an apartment lock and can be unlocked for operation with either key A-1 or B-1. Generator breaker G interlock can be unlocked for operation with key B-1 only.

To transfer load N to breaker A, proceed as follows:

  1.
2.

3.

4.
Open breaker B.
Turn key B-1 in L-O interlock on breaker B to lock open. Key B-1 is now free.
Insert Key B-1 in L-O interlock on tie-breaker C and turn to unlock. Key B-1 is now held.
Close tie-breaker C.

Reverse sequence to restore service through breaker B. Load M can be supplied through breaker B in a similar manner.

To transfer load N to the generator, proceed as follows:

  1.
2.

3.

4.
Open breaker B.
Turn key B-1 in L-O interlock on breaker B to lock open. Key B-1 is now free.
Insert key B-1 in L-O interlock on generator breaker G and turn to unlock. Key B-1 is now held.
Close generator breaker G.

Reverse sequence to restore service through breaker B.

To transfer loads M and N to the generator, proceed as follows:

  1.
2.

3.
4.

5.

6.
7.

8.
Open breaker A.
Turn key A-1 in L-O interlock on breaker A to lock open. Key A-1 is now free.
Open breaker B.
Turn key B-1 in L-O interlock on breaker B to lock open. Key B-1 is now free.
Insert key A-1 in L-O interlock on tie-breaker C and turn to unlock. Key A-1 is now held.
Close tie-breaker C.
Insert key B-1 in L-O interlock on generator breaker G and turn to unlock. Key B-1 is now held.
Close generator breaker G.

Reverse sequence to restore service through breakers A and B.


Links for more interlock application scheme information:

Contents | Introduction | Symbols Legend | Scheme Book

Scheme # 25
Scheme # 26
Scheme # 27
Scheme # 28
Scheme # 29
Scheme # 30
Scheme # 31
Scheme # 32

Scheme # 33 Scheme # 34
Scheme # 35
Scheme # 35A

Scheme # 36

Scheme # 37
Scheme # 38
Scheme # 39
Scheme # 40
Scheme # 41
Scheme # 42
Scheme # 42A
Scheme # 42B

Scheme # 43
Scheme # 43A
Scheme # 44
Scheme # 45
Scheme # 45A

 
   

Copyright © 2000-2007 Kirk Key Interlock. All Rights Reserved.
Terms and Conditions
Web Site, Graphics & Design by R.S.Venables