Scheme # 36
To prevent paralleling of any sources while allowing switching
of the loads to alternate sources.

Breaker A is closed to supply load M. Breaker B is closed
to supply load N. Tie-Breaker C and generator breakers
G and H are locked open. Key A-1 is held in the L-O interlock
on breaker A. Key B-1 is held in the L-O interlock on
breaker B. Tie-Breaker C cannot be closed unless either
breaker A or breaker B is locked open. Generator breaker
G cannot be closed unless breaker B is locked open. Generator
breaker H cannot be closed unless breaker A is locked
open. Tie-Breaker C interlock has an apartment lock and
can be unlocked for operation with either key A-1 or B-1.
Generator G breaker interlock can be unlocked for operation
with key B-1 only. Generator H breaker interlock can be
unlocked for operation with Key A-1 only.
To
transfer load N to breaker A, proceed as follows:
|
|
1.
2.
3.
4. |
Open breaker B.
Turn key B-1 in L-O interlock on breaker B to lock
open. Key B-1 is now free.
Insert Key B-1 in L-O interlock on tie-breaker C and
turn to unlock. Key B-1 is now held.
Close tie-breaker C. |
Reverse
sequence to restore service through breaker B. Load M
can be supplied through breaker B in a similar manner.
To
transfer load M to generator H, proceed as follows:
|
|
1.
2.
3.
4.
|
Open breaker A.
Turn key A-1 in L-O interlock on breaker A to lock
open. Key A-1 is now free.
Insert key A-1 in L-O interlock on generator breaker
H and turn to unlock. Key A-1 is now held.
Close generator breaker H. |
Reverse
sequence to restore service through breaker A.
Load N can be transferred to generator G using the B-1
key in a similar manner.
To
transfer loads M and N to generator H, proceed as follows:
|
|
1.
2.
3.
4.
5.
6.
7.
8. |
Open breaker A.
Turn key A-1 in L-O interlock on breaker A to lock
open. Key A-1 is now free.
Open breaker B.
Turn key B-1 in L-O interlock on breaker B to lock
open. Key B-1 is now free.
Insert key B-1 in L-O interlock on tie-breaker C and
turn to unlock. Key B-1 is now held.
Close tie-breaker C.
Insert key A-1 in L-O interlock on generator breaker
H and turn to unlock. Key A-1 is now held.
Close generator breaker H. |
Reverse
sequence to restore service through breakers A and B.
Loads M and N can be transferred to generator G in a similar
manner. Open breakers A & B, then utilize the A-1
key to unlock tie-breaker C and utilize the B-1 key to
unlock generator breaker G.

|