Interlock Application - Isolating Switches and Breaker

Scheme # 8

To prevent operation of disconnects A and B when breaker C is closed. To permit servicing of breaker when disconnects are locked open.

Interlock Application Scheme # 8  - Isolating Switches and Breaker

Breaker C and disconnects A and B are shown closed. One key A-1 is held in breaker L-O interlock and the other key A-1 is held in L-O interlock on disconnect B. Key A-2 is held in L-O interlock on disconnect A.

1.
2.

3.

4.
5.

6.

7.
8.

9.
Open breaker.
Turn key A-1 in L-O interlock on breaker to lock open. Key A-1 is now free.
Insert key A-1 in L-C interlock on disconnect A and turn to unlock. Key A-1 is now held.
Open disconnect A.
Turn key A-2 in L-O interlock on disconnect A to lock open. Key A-2 is now free.
Insert key A-2 in L-C interlock on disconnect B and turn to unlock. Key A-2 is now held.
Open disconnect B.
Turn key A-1 in L-O interlock on disconnect B to lock open. Key A-1 is now free.
Insert key A-1 in breaker L-O interlock and turn to unlock for operation during servicing.

Reverse sequence to restore service.

Links for more interlock application scheme information:

Contents | Introduction | Symbols Legend | Scheme Book

Scheme # 25
Scheme # 26
Scheme # 27
Scheme # 28
Scheme # 29
Scheme # 30
Scheme # 31
Scheme # 32

Scheme # 33 Scheme # 34
Scheme # 35
Scheme # 35A

Scheme # 36

Scheme # 37
Scheme # 38
Scheme # 39
Scheme # 40
Scheme # 41
Scheme # 42
Scheme # 42A
Scheme # 42B

Scheme # 43
Scheme # 43A
Scheme # 44
Scheme # 45
Scheme # 45A

 
   

Copyright © 2000-2007 Kirk Key Interlock. All Rights Reserved.
Terms and Conditions
Web Site, Graphics & Design by R.S.Venables