Interlock
Application Schemes
Examples
of typical interlock schemes to help you design your own schemes.
Application
Schemes - Table Of Contents
Introduction
Symbols Legend
Scheme
Book - Printable
Switch and
Breaker
Scheme # 1
Prevents opening of switch when breaker is closed.
Scheme # 2
Prevents operation of switch when breaker is closed. Permits re-closing
the breaker for servicing when switch is locked open.
Scheme
# 3
Prevents operation of switch when breaker is closed. Circuit cannot
be cleared until proper supervisory key is obtained.
Grounding Switch
with Main Switch
Scheme
# 4
Prevents closing of grounding switch when main switch is closed,
and vice versa.
Isolating
Switches and Breaker
Scheme
# 5
Prevents
operation of disconnect when breaker is closed. Prevents opening
fuse compartment door when disconnect is closed.
Scheme
# 6
Prevents operation of disconnect when any or all of a group of breakers
are closed. Operates through transfer interlock, no sequence is
required for breaker closing.
Scheme
# 7
Prevents operation of disconnect when any or all of a group of breakers
are closed. Breakers operated in prearranged sequence.
Scheme # 8
Prevents operation of disconnects when breaker is closed. Permits
servicing of breaker when disconnects are locked open.
Scheme # 9
Prevents operation of disconnects when breaker is closed, and prevents
access to breaker compartment with disconnects closed.
Isolating
Switches and Breaker Isolating Switches and Breaker or Regulator
with By-Pass Switch
Scheme
# 10
Prevents operation of breaker disconnects and by-pass disconnect
under load. Provides for closing of by-pass disconnect before circuit
is opened, or permits circuit breaker to be opened with by-pass
disconnect remaining open.
Scheme
# 10A
Prevents operation of voltage regulator disconnects and by-pass
disconnect under load. Permits by-pass disconnect to operate only
when regulator is in neutral position. Permits isolating regulator
for servicing.
Prevent
Paralleling of Lines
Scheme
# 11
Prevents paralleling of two lines - single load, fed from either
source.
Scheme
# 12
Prevents paralleling of two lines - single load, fed from either
source - breaker on load side.
Scheme
# 13
Prevents paralleling of two lines - two loads, fed from either source
(one tie breaker).
Scheme # 14
Prevents paralleling of two lines - two loads, fed from either source
(one tie breaker). Prevents operation of switch when breaker is
closed (on either source).
Scheme # 15
Prevents paralleling of two lines - two loads fed from either source
(one tie breaker). Prevents operation (open or closed) of disconnect
when breaker is closed (on either source). Prevents access to fuses
when disconnects and breakers are closed.
Scheme
# 16
Prevents paralleling of three lines - three loads, fed from any
source (two tie breakers).
Scheme
# 17
Prevents paralleling
of four lines - four loads fed from any source (three tie breakers).
Scheme # 17A
Prevents paralleling
of four lines - four loads fed from any source (three tie breakers).
Also prevents opening of rear access doors when breakers are energized.
Scheme # 18
Prevents paralleling of three lines - three loads fed from any source
(three tie breakers).
Scheme
# 19
Prevents paralleling
of four lines - four loads fed from any source (four tie breakers).
Scheme
# 20
Prevents paralleling
of three power sources through a common tie bus not normally in
service. Permits feeding any load bus from a second power source
through the tie bus. Permits one power source to supply all three
load buses through the tie bus.
Scheme
# 21
Prevents paralleling
three power sources through a common tie bus not normally in service.
Permits feeding any load bus from a second power source through
the tie bus only when authorized by a supervisor. Permits one power
source to supply all three load buses through the tie bus only when
authorized by a supervisor.
Scheme
# 22
Prevents paralleling
two incoming primary sources through primary tie bus disconnect.
Prevents operation (open or closed) of the disconnects under load.
Permits one power source to supply both loads through tie bus.
Scheme
# 23
Prevents paralleling of two incoming primary sources through the
primary tie bus disconnect or secondary tie bus breaker. Prevents
operation (open or closed) of disconnects under load. Permits one
power source to supply both loads through either the primary or
secondary tie bus.
Scheme
# 24
Prevents paralleling
of two incoming primary sources. Prevents operation (open or closed)
of disconnects under load. Permits the isolating of breakers for
servicing. Permits one power source to supply both loads through
tie bus.
Interrupter
Switch
Scheme
# 25
Prevents opening
fuse compartment door when the interrupter switch is closed. Prevents
closing interrupter switch until fuse compartment door is locked
closed.
Scheme
# 26
Prevents operation
(open or closed) of interrupter switch when breaker is closed. Permits
the breaker to be serviced and operated while the interrupter switch
is locked open.
Scheme
# 27
Prevents operation
(open or closed) of interrupter switch when breaker is closed. Prevents
opening fuse compartment door when interrupter switch is closed.
Prevents closing interrupter switch until fuse compartment door
is locked closed. Permits the breaker to be serviced and operated
while the interrupter switch is locked open.
Scheme
# 28
Prevents dropping load when shifting from one source to the other.
Prevents opening both interrupter switches at the same time. Permits
both interrupter switches to be closed at the same time.
Scheme # 29
Prevents paralleling two lines requires dropping load when shifting
from one source to the other. Prevents closing both interrupter
switches at the same time. Permits both interrupter switches to
be opened at the same time.
Scheme # 30
Prevents paralleling two lines requires dropping load when shifting
from one source to the other. Prevents closing both interrupter
switches at the same time.Permits both interrupter switches to be
open at the same time. Prevents operation (open or closed) of either
interrupter switch when breaker is closed. Permits the breaker to
be serviced and operated while both interrupter switches are locked
open.
Scheme # 31
Prevents operation (closed, open or closed) of the a three position
interrupter switch when the breaker is closed.Permits the breaker
to be serviced and operated while the interrupter switch is locked
open.
Scheme # 32
Prevents operation (closed, open or closed) of a three position
interrupter switch when the breaker is closed. Prevents opening
fuse compartment door when the interrupter switch is closed. Prevents
closing interrupter switch until fuse compartment door is locked
closed. Permits the breaker to be serviced and operated while the
interrupter switch is locked open.
Motor or
Machinery Guard
Scheme # 33
Prevents opening of guard when motor circuit is closed. Guard may
be a door or fence gate that prevents access to moving parts, belts,
cutters, or any dangerous equipment.
Motor or
Machinery Guard with Time Delay
Scheme # 34
Prevents opening of guard (or door) for a predetermined time after
removal of power (from motor, centrifuge, condensers, etc.).
Breakers
and Generators
Scheme # 35
Prevents paralleling of two lines - two loads, fed from either source
(one tie breaker). Allows switching loads to a generator.
Scheme
# 35A
Prevents closing generator breaker when main breaker is closed.
Scheme
# 36
Prevents paralleling of two lines - two loads, fed from either source
(one tie breaker). Allows switching loads to two generators.
Capacitor
Bank Access
Scheme # 37
Prevents access to capacitor bank enclosure until capacitors have
been grounded and discharged.
Scheme
# 38
Prevents access to capacitor bank enclosure until capacitors have
been grounded and discharged - utilizing a Time Delay Key Release
Unit (TDKRU).
Uninterrupted
Power Sources
Scheme # 39
Prevents improper maintenance bypass of UPS equipment.
Scheme
# 40
Prevents improper maintenance bypass of UPS equipment.
Precipitator
Access
Scheme # 41
Prevents access to an electrostatic precipitator, scrubber, or baghouse
until all power supplies have been de-energized and properly grounded.
Scheme
# 42
To allow operation of dual output transformer rectifiers with one
field removed from service and to prevent opening any access doors
of an electrostatic precipitator until all power supplies are de-energized
and properly grounded.
Scheme
# 42A
To allow operation of dual output transformer rectifiers with one
field removed from service and to prevent opening any access doors
of an electrostatic precipitator until all power supplies are de-energized
and properly grounded.
Scheme
# 42B
To allow operation of dual output transformer rectifiers with one
field removed from service and to prevent opening any access doors
of an electrostatic precipitator until all power supplies are de-energized
and properly grounded.
Rectifier
Access
Scheme # 43
Prevents opening any rectifier enclosure door while the rectifier
is operating.
Scheme
# 43A
Prevents opening any rectifier enclosure door while the rectifier
is operating.
Scheme
# 44
Prevents opening any rectifier enclosure door while the rectifier
is operating.
Scheme
# 45
Prevents opening any rectifier enclosure door while the rectifier
is operating and prevents opening the negative disconnect
switch under load.
Scheme
# 45A
Prevents opening any rectifier enclosure door while the rectifier
is operating and prevents opening the negative disconnect
switch under load.